dc.description.abstractSchedule management is a particularly important activity for companies that manage their business with an engineer-to-order approach. In many cases, especially in smaller enterprises, projects duration, estimated applying deterministic approaches or even referring to own experiences, are significantly inaccurate or overestimated. For these reasons, in this paper which is the extended version of a previous work presented at the Summer School "F. Turco", authors propose an application of a probabilistic simplified approach on a case study comparing the results to those deriving from deterministic approaches and actual durations. Methodologies have been applied according to the sequence defined by the Project Management Institute. To estimate activities durations both physical and statistical models have been used, instead of the entire project duration has been calculated through a critical path method. Results comparison shows that adopting a statistical approach leads to tolerable complications but allows to get more accurate estimations. Moreover, the possibility to consider the most probable, optimistic and pessimistic duration allows the enterprise to take into account potential risks that could delay project conclusion. This application is focused on a particular case study nevertheless conclusion could be common to many other organizations.it
dc.language.isoengit
dc.titleEngineer-to-order Project Schedule Planning through a probabilistic simplified approach: A case studyit
dc.typearticle*
dc.identifier.doi10.19255/JMPM02108it
dc.identifier.scopus2-s2.0-85119380783it
dc.identifier.urlhttps://api.elsevier.com/content/abstract/scopus_id/85119380783it
dc.relation.journalJOURNAL OF MODERN PROJECT MANAGEMENTit
dc.relation.firstpage190it
dc.relation.lastpage214it
dc.relation.volume7it
dc.relation.issue3it
dc.contributor.countryITAit
dc.type.miur262*
item.fulltextWith Fulltext-
item.openairetypearticle-
item.cerifentitytypePublications-
item.grantfulltextrestricted-
item.languageiso639-1en-
item.openairecristypehttp://purl.org/coar/resource_type/c_18cf-
crisitem.journal.journalissn2317-3963-
crisitem.journal.anceE222891-
Appears in Collections:A1. Articolo in rivista
Files in This Item:
File Description SizeFormat Existing users please
eNGINEERING TO ORDER PROJECT.pdf594.54 kBAdobe PDF    Request a copy
Show simple item record

Page view(s)

87
Last Week
0
Last month
2
checked on Apr 24, 2024

Download(s)

3
checked on Apr 24, 2024

Google ScholarTM

Check

Altmetric


All documents in the "Unitus Open Access" community are published as open access.
All documents in the community "Prodotti della Ricerca" are restricted access unless otherwise indicated for specific documents